What Is a Change Order and When Do I Need One?

A change order is a short written document that describes a change to the agreed work, its effect on price and schedule, and the customer’s approval. Get it approved before you do any meaningful out-of-scope work. Attach it to the original job so the final invoice matches what the customer agreed to.

Changes come from two places:

  • Customer requests. “Can you add the back fence too?”
  • Required changes. Hidden damage, code requirements, or a wrong assumption in the estimate (see 11.1.2 Estimate).

Train yourself and your team to spot them. If it’s not in the scope, it’s a change (see 11.1.4 Scope of Work).

Calculate the added or reduced cost: labor, materials, equipment, and any fees. Show the new total, not just the difference, so the customer sees the full picture.

Say how the change affects the start, finish, or delivery date. Even a free change can delay the job.

Get written approval before you proceed, when your agreement or the law requires it, and as a habit for anything meaningful. Approval can be a signature, an e-signature, or a reply that clearly accepts the specific change. The federal Electronic Signatures in Global and National Commerce Act (E-Sign Act) gives electronic signatures and records general legal validity for many transactions. Ask your attorney what counts as approval in your state and trade.

Number each change order and attach it to the original job record and agreement. Your invoice should list the original price and each approved change (see 10.7.5 Invoices).

Don’t let anyone do out-of-scope work without an approved change order. If a true emergency requires action, like stopping a leak, document it right away with photos and get approval as soon as you can. Your agreement should say how emergencies are handled.

Made-up example: During a bathroom remodel, Stonebridge Builders finds rotted subfloor. The crew stops, takes photos, and the project lead writes Change Order 2: replace 30 square feet of subfloor, adds a set amount, adds two days. The homeowner signs on a tablet before the crew continues. The final invoice lists the original price plus Change Orders 1 and 2.

  • Unapproved extras often go unpaid. Customers push back on charges they didn’t approve.
  • Surprise bills cause disputes, chargebacks, and bad reviews.
  • Schedule changes without notice frustrate customers even when the work is good.
  • Customers are told to expect it. The Federal Trade Commission (FTC) tells homeowners to get every promise about the work and cost in the written contract.
  • Good records protect you if there’s a complaint or a legal claim.

Any business doing project or custom work. Even small businesses with simple jobs benefit from a one-page form. Fixed-price, standard services rarely need them.

  1. Put a change clause in your agreement that requires written approval for scope, price, or schedule changes (see 11.1.1 Service Agreement).
  2. Create a one-page change order form: job name, change order number, description, reason, price impact, new total, schedule impact, and approval line.
  3. Stop and write it up as soon as a change comes up.
  4. Explain the change in plain words. Add photos for hidden conditions.
  5. Get approval before doing the work, in writing or by e-signature.
  6. Attach the change order to the job record and agreement.
  7. Update the schedule and tell anyone affected (see 22.5 Scheduling and Delivery Procedure).
  8. Show every change on the invoice.
  9. Review change orders monthly. If the same change keeps coming up, fix your estimates or scope.
  • Each numbered change order with approval
  • Photos of hidden conditions
  • Updated schedule notices
  • The invoice showing the original price and approved changes
  • Any notes on emergency work done before approval
  • Saying “we’ll figure it out later.” Later is when disputes happen.
  • Approving changes on the phone only.
  • Showing only the added cost, not the new total.
  • Forgetting the schedule impact.
  • Crew members agreeing to extras on site without telling the office.
  • Billing for changes that were never approved.

An attorney to review your change clause and form, especially in construction where state rules may apply. Questions to ask:

  • What counts as written approval in my state and trade?
  • How should my agreement handle emergency work?
  • Are there state rules on change orders for home improvement work?

[Bill: add a short note. For example, how SiteSmarty handles extra requests during a website build, or a client story where a missing change order turned into a dispute.]

  • [Date I did this:]
  • [What I actually did, step by step: the SiteSmarty change order form and approval process]
  • [What it cost and how long it took:]
  • [What surprised me or what I’d do differently:]
  • [Screenshot or photo to add, with private info blurred: a filled-in change order with approval]
  • [Result so far:]

When do I need a change order? Any time the work, price, or schedule changes from what the customer agreed to, before you do the work.

Can a customer approve by email or text? Often, if the message clearly accepts the specific change. The E-Sign Act gives electronic records general validity, but ask your attorney what your state and trade require.

What if I already did the extra work? Write it up right away, explain it, and ask for approval. Without prior approval, you may not get paid.

Should a change order show the new total? Yes. Show the original price, the change, and the new total.

LineQuestionPass looks likeFail looks likeEvidence to collect
11.1.5 Change orderIs every material out-of-scope change approved in writing before work?Numbered, approved change orders on fileVerbal changes, surprise chargesChange orders and job records
17.6.1 Change identificationDoes the team identify changes as they come up?Changes written up when foundExtras discovered at billingJob notes and change orders
17.6.2 Price impactIs the cost of each change calculated and shown?Change amount and new totalNo price, or “to be decided”Change orders
17.6.3 Schedule impactIs the timing impact stated?New dates on the change orderNo schedule noteChange orders, schedule
17.6.4 Customer approvalIs approval obtained before proceeding when required?Signed or clearly accepted firstApproval after the factApproval records with dates
17.6.5 RecordkeepingAre change orders attached to the original job?Linked to job and invoiceLoose or missingJob file and invoice
17.6.6 Unauthorized workIs out-of-scope work prevented without approval?No unapproved extras, emergencies documentedCrew does extras freelyJob files, invoices, crew notes

Where this fits

Do this first: 11.1.4 Scope of Work, 11.1.1 Service Agreement

Do this next: 11.1.6 Payment Terms

Related pages: 11.1.2 Estimate, 10.7.3 Progress Payments, 10.7.5 Invoices, 17.5 Project Delivery, 17.8 Complaint Handling, 22.5 Scheduling and Delivery Procedure, 14.6.3 Review Responses

Sources

This page explains general rules and Bill's own experience. It is not legal, tax, or insurance advice. Talk to a qualified professional about your situation.