What Is a Change Order and When Do I Need One?
The short answer
Section titled “The short answer”A change order is a short written document that describes a change to the agreed work, its effect on price and schedule, and the customer’s approval. Get it approved before you do any meaningful out-of-scope work. Attach it to the original job so the final invoice matches what the customer agreed to.
What this means
Section titled “What this means”17.6.1 Change identification
Section titled “17.6.1 Change identification”Changes come from two places:
- Customer requests. “Can you add the back fence too?”
- Required changes. Hidden damage, code requirements, or a wrong assumption in the estimate (see 11.1.2 Estimate).
Train yourself and your team to spot them. If it’s not in the scope, it’s a change (see 11.1.4 Scope of Work).
17.6.2 Price impact
Section titled “17.6.2 Price impact”Calculate the added or reduced cost: labor, materials, equipment, and any fees. Show the new total, not just the difference, so the customer sees the full picture.
17.6.3 Schedule impact
Section titled “17.6.3 Schedule impact”Say how the change affects the start, finish, or delivery date. Even a free change can delay the job.
17.6.4 Customer approval
Section titled “17.6.4 Customer approval”Get written approval before you proceed, when your agreement or the law requires it, and as a habit for anything meaningful. Approval can be a signature, an e-signature, or a reply that clearly accepts the specific change. The federal Electronic Signatures in Global and National Commerce Act (E-Sign Act) gives electronic signatures and records general legal validity for many transactions. Ask your attorney what counts as approval in your state and trade.
17.6.5 Recordkeeping
Section titled “17.6.5 Recordkeeping”Number each change order and attach it to the original job record and agreement. Your invoice should list the original price and each approved change (see 10.7.5 Invoices).
17.6.6 Unauthorized work
Section titled “17.6.6 Unauthorized work”Don’t let anyone do out-of-scope work without an approved change order. If a true emergency requires action, like stopping a leak, document it right away with photos and get approval as soon as you can. Your agreement should say how emergencies are handled.
Made-up example: During a bathroom remodel, Stonebridge Builders finds rotted subfloor. The crew stops, takes photos, and the project lead writes Change Order 2: replace 30 square feet of subfloor, adds a set amount, adds two days. The homeowner signs on a tablet before the crew continues. The final invoice lists the original price plus Change Orders 1 and 2.
Why it matters
Section titled “Why it matters”- Unapproved extras often go unpaid. Customers push back on charges they didn’t approve.
- Surprise bills cause disputes, chargebacks, and bad reviews.
- Schedule changes without notice frustrate customers even when the work is good.
- Customers are told to expect it. The Federal Trade Commission (FTC) tells homeowners to get every promise about the work and cost in the written contract.
- Good records protect you if there’s a complaint or a legal claim.
Who this applies to
Section titled “Who this applies to”Any business doing project or custom work. Even small businesses with simple jobs benefit from a one-page form. Fixed-price, standard services rarely need them.
How to do it
Section titled “How to do it”- Put a change clause in your agreement that requires written approval for scope, price, or schedule changes (see 11.1.1 Service Agreement).
- Create a one-page change order form: job name, change order number, description, reason, price impact, new total, schedule impact, and approval line.
- Stop and write it up as soon as a change comes up.
- Explain the change in plain words. Add photos for hidden conditions.
- Get approval before doing the work, in writing or by e-signature.
- Attach the change order to the job record and agreement.
- Update the schedule and tell anyone affected (see 22.5 Scheduling and Delivery Procedure).
- Show every change on the invoice.
- Review change orders monthly. If the same change keeps coming up, fix your estimates or scope.
What proof to keep
Section titled “What proof to keep”- Each numbered change order with approval
- Photos of hidden conditions
- Updated schedule notices
- The invoice showing the original price and approved changes
- Any notes on emergency work done before approval
Common mistakes
Section titled “Common mistakes”- Saying “we’ll figure it out later.” Later is when disputes happen.
- Approving changes on the phone only.
- Showing only the added cost, not the new total.
- Forgetting the schedule impact.
- Crew members agreeing to extras on site without telling the office.
- Billing for changes that were never approved.
When to get help from a pro
Section titled “When to get help from a pro”An attorney to review your change clause and form, especially in construction where state rules may apply. Questions to ask:
- What counts as written approval in my state and trade?
- How should my agreement handle emergency work?
- Are there state rules on change orders for home improvement work?
Bill’s note
Section titled “Bill’s note”[Bill: add a short note. For example, how SiteSmarty handles extra requests during a website build, or a client story where a missing change order turned into a dispute.]
How I did this for SiteSmarty
Section titled “How I did this for SiteSmarty”- [Date I did this:]
- [What I actually did, step by step: the SiteSmarty change order form and approval process]
- [What it cost and how long it took:]
- [What surprised me or what I’d do differently:]
- [Screenshot or photo to add, with private info blurred: a filled-in change order with approval]
- [Result so far:]
Questions people ask
Section titled “Questions people ask”When do I need a change order? Any time the work, price, or schedule changes from what the customer agreed to, before you do the work.
Can a customer approve by email or text? Often, if the message clearly accepts the specific change. The E-Sign Act gives electronic records general validity, but ask your attorney what your state and trade require.
What if I already did the extra work? Write it up right away, explain it, and ask for approval. Without prior approval, you may not get paid.
Should a change order show the new total? Yes. Show the original price, the change, and the new total.
Audit check
Section titled “Audit check”| Line | Question | Pass looks like | Fail looks like | Evidence to collect |
|---|---|---|---|---|
| 11.1.5 Change order | Is every material out-of-scope change approved in writing before work? | Numbered, approved change orders on file | Verbal changes, surprise charges | Change orders and job records |
| 17.6.1 Change identification | Does the team identify changes as they come up? | Changes written up when found | Extras discovered at billing | Job notes and change orders |
| 17.6.2 Price impact | Is the cost of each change calculated and shown? | Change amount and new total | No price, or “to be decided” | Change orders |
| 17.6.3 Schedule impact | Is the timing impact stated? | New dates on the change order | No schedule note | Change orders, schedule |
| 17.6.4 Customer approval | Is approval obtained before proceeding when required? | Signed or clearly accepted first | Approval after the fact | Approval records with dates |
| 17.6.5 Recordkeeping | Are change orders attached to the original job? | Linked to job and invoice | Loose or missing | Job file and invoice |
| 17.6.6 Unauthorized work | Is out-of-scope work prevented without approval? | No unapproved extras, emergencies documented | Crew does extras freely | Job files, invoices, crew notes |
Where this fits
Do this first: 11.1.4 Scope of Work, 11.1.1 Service Agreement
Do this next: 11.1.6 Payment Terms
Related pages: 11.1.2 Estimate, 10.7.3 Progress Payments, 10.7.5 Invoices, 17.5 Project Delivery, 17.8 Complaint Handling, 22.5 Scheduling and Delivery Procedure, 14.6.3 Review Responses
Sources
- Federal Deposit Insurance Corporation (FDIC) Consumer Compliance Examination Manual, "Electronic Signatures in Global and National Commerce Act" (checked October 17, 2026)
- Federal Trade Commission, "How To Avoid a Home Improvement Scam" (checked October 17, 2026)
- Google Business Profile Help, "Tips to improve your local ranking on Google" (checked October 17, 2026)
This page explains general rules and Bill's own experience. It is not legal, tax, or insurance advice. Talk to a qualified professional about your situation.